Prolongation in construction contracts
As per the definition contained in the Society of Construction Law Delay and Disruption Protocol the term ‘prolongation’ refers to 'the extended duration of the works during which time-related costs are incurred as a result of a delay' - usually recognised as the additional projected time required to complete a contract extending beyond the contractual completion date.
Prolongation costs are the additional costs that a contractor has incurred as a result of the completion of the works being delayed by an event that is the responsibility of the other party (usually the Employer). Such events might include; failing to give the contractor possession of the site on the date specified in the contract; delays in giving instructions, and so on.
The contractor may incur additional costs as a result of having to remain on site for longer than anticipated, for example, additional labour costs, plant costs, off-site overheads, fluctuations, and so on.
Prolongation is sometimes described as being synonymous with ‘loss and expense’, however, this is incorrect. Loss and expense is a wider term that refers to matters which are the responsibility of the client that materially affect the progress of the works. This includes matters that disrupt, rather than delay the progress of the works, but still entitle the contractor to make a claim for additional costs incurred. Claims for disruption result from the additional cost of adopting inefficient working methods as a result of the disruption.
For more information, see Disruption claims in construction.
Prolongation and disruption therefore are two separate elements that might result in a claim for loss and expense. The prolongation element is dependent on the completion date being delayed.
Depending on the terms of the construction contract, prolongation might relate to the project as a whole, or to a specific aspect of it.
Generally a disruption event is easier to prove than a critical delay prolongation event i.e. a failed critical delay prolongation claim will often be used as proof of disruption. However, prolongation costs are often considered easier to demonstrate than disruption costs.
For more information see: Loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this.